Polymer Dosing Calculator
Flocculant make-down and dosing rates from slurry mass balance — feed rate, dilution and pump duty for a target dose.
Inputs
Blue = editablem³
%
–
%
m³/hr
kg/MTds
%
Results
LiveMass balance
Porosity––
Water volume–m³
Solids volume–m³
Solids weight–t
Dosing
Dry-bone dose rate–MTds/hr
Polymer feed rate–kg/hr
Parts water (make-down)–:1
Diluted polymer pump flow–L/hr
Diluted polymer dose rate–ppm
PPM dose rate (undiluted)–ppm
Total polymer required (batch)–kg
Note: Polymer dose is highly tailings-specific and should be confirmed from bench / pilot flocculation trials, not a rule of thumb. Make-down dilution and pump duty are theoretical; verify against the dosing skid's operating envelope. Specific gravity assumes a single mineral phase.
Geobag Tailings Cost Model
Cost-per-dry-tonne (AUD/DMT) built from a solids mass balance, with every cost tied to a physical driver and split into tonnage-variable vs fixed/time-based.
Inputs
Blue = editable1 · Project basis
dry t/yr
yr
d/yr
hr
2 · Tailings & dewatering
t/m³
3 · Geobag geometry & supply
m³/lm
m
$/lm
4 · Polymer
kg/t
$/kg
$/mo
5 · Labour
lm/shift
ppl
$/hr
ppl
$/hr
hr/d
$/hr
hr/d
$/hr
6 · Accommodation & mobilisation
ppl
$/n
frac
$
7 · Civil works
m²
$/m²
$
$
8 · Equipment & pumping
$/mo
$
$/d
9 · Commercial
%
Results — base case
LiveTotal installed cost–$/DMT
Direct cost–$/DMT
Total project cost–$
Total dry tonnes stored–DMT
Quantities
Geobag lineal metres required–lm
Standard bag units–no.
Deployment shifts–no.
Cost breakdown (direct)
$/DMT split
Tonnage-variable–$/DMT
Fixed / time-based–$/DMT
Sensitivity — $/DMT vs annual throughput
| DMT/yr | $/DMT total |
|---|
Fixed costs are diluted as tonnage rises — which is why $/DMT falls across the scenario rows. The scenarios hold project life & all unit rates constant and vary only annual throughput.
Planning / comparison tool — figures are illustrative until project-specific inputs are populated. Replace geobag $/lm, polymer dose & $/kg, and all rental/labour rates with quoted / bench-tested values. Final dry density is the single biggest driver of stored volume — confirm it for your tailings. Excludes (unless added): return-water collection/treatment, double-handling, closure/capping, royalties, GST and finance costs. Commercial, contractual and regulatory matters should be verified with the relevant suppliers and advisors.
Geotextile Tube Fill-Height Calculator
Physics-first: maximum safe fill height is the lower of hoop tension, rolling stability and the geometric ceiling — no empirical fill-height table.
Inputs
Blue = editableA · Slurry properties
–
–
B · Bag geometry
m
C · Fabric properties
kN/m
–
D · Engineering parameters
–
–
–
Results
LiveDerived slurry & geometry
Slurry density, ρ_mix–kg/m³
Hydrostatic gradient, γ–kPa/m
Theoretical diameter, D = C/π–m
Design tension, T_design–kN/m
Calculated fill heights
Hoop-tension limit–m
Stability limit–m
Geometric ceiling–m
Operating fill height, h_op–m
Operating pressures
Base hydrostatic pressure at h_op–kPa
Target pump pressure (90%)–kPa
Hard pressure cap (105%)–kPa
Capacity (volume per metre)
h/D at h_op––
Volume / m at max pump height–m³/m
Volume / m at 75% settled–m³/m
Capacity utilisation–%
Method: h_max = MIN of three independent limits — (1) hoop tension h = √(T_design / (k·ρ·g)), independent of circumference; (2) stability h ≤ (h/D)_max·D; (3) geometry h ≤ D = C/π. Use pressure (kPa) for real-time operator control — it is more reliable than measuring height on imperfect foundations. After consolidation a second fill pass is usually possible; recalculate using the consolidated surface as the new datum. Always confirm with a bench / pillow test on the actual slurry where consequences of failure are material.
Geotextile Tube Volume Calculator
Volume from circumference & fill height using the empirical cross-section formula.
Inputs
Blue = editableV = L · D² · [ (h/D)^0.815 − (h/D)^8.6 ] where D = C / π
m
m
m
m
Results
LiveTheoretical diameter, D–m
Fill ratio, h/D (settled)––
Cross-section area, A–m²
Volume per metre–m³/m
Total volume–m³
Assumptions: D = C/π (theoretical diameter the section would have if filled to a full circle). Exponents 0.815 and 8.6 are an empirical fit — validate outputs against the manufacturer's published volume / fill tables before relying on them for design. Cross-section area peaks at h/D ≈ 0.74 then declines (a mathematical artefact of the form). Units are consistent-length agnostic (m → m³). General guidance only — confirm site-specific limits and good engineering practice.
Geotube Sizing & Dewatering Mass Balance
Tracks solids and water through three states — original slurry, pumped into the tube, and dewatered — then sizes the length and number of tubes required from the dewatered volume.
Inputs
Blue = editablen = G(1−S) / [ G(1−S) + S ] · V/m = D²·[(h/D)^0.815 − (h/D)^8.6]
Slurry & solids
m³
–
%
%
%
Pumping
m³/hr
Tube selection
m
m
m
m
Results
LiveMass balance
| Property | Original | Into tube | Dewatered |
|---|
Tube sizing
Length of tube required–m
Number of tubes (rounded up)–units
Number of tubes (exact)–units
Tube capacity
Theoretical diameter, D = C/π–m
Volume / m at max fill height–m³/m
Volume / m at settled height–m³/m
Pumping
Volume pumped into tube–m³
Time to pump at pump rate–hr
Method: porosity n = G(1−S)/[G(1−S)+S] from solids SG (G) and solids mass fraction (S). Solids volume and bone-dry solids weight are conserved across all three states; water volume is recomputed at each state's porosity (water density = 1.0 t/m³). Tube volume per metre uses the empirical section formula (exponents 0.815 & 8.6, peak at h/D ≈ 0.74); validate against the manufacturer's published volume / fill tables before relying on it for design. Length required = dewatered volume ÷ settled volume per metre. Planning tool — confirm site-specific values and good engineering practice.