Kontain

Geobag Calculator Suite

This tool is shared by Kontain Solutions. Enter the access code provided to you to continue.

Provided by Kontain Solutions
Ben Lewis · ben.lewis@kontainsolutions.com
Geobag dewatering & containment — engineering calculator suite
Not for construction · estimates only. These tools provide preliminary planning estimates only and are based entirely on user-entered assumptions. They are not certified design outputs, construction advice, regulatory approval, or a substitute for project-specific engineering review. Kontain has not verified all project conditions, including sediment properties, geotechnical conditions, hydraulics, chemistry, site access, environmental approvals, safety requirements, constructability, installation constraints, or third-party product performance. Outputs apply only to Kontain products and indicative Kontain geobag/geotextile tube applications where those products are specifically selected. To the maximum extent permitted by law, Kontain accepts no liability for reliance on these outputs, incorrect assumptions, or use outside confirmed product capability.

Polymer Dosing Calculator

Flocculant make-down and dosing rates from slurry mass balance — feed rate, dilution and pump duty for a target dose.

Inputs

Blue = editable
%
%
m³/hr
kg/MTds
%

Results

Live
Mass balance
Porosity
Water volume
Solids volume
Solids weightt
Dosing
Dry-bone dose rateMTds/hr
Polymer feed ratekg/hr
Parts water (make-down):1
Diluted polymer pump flowL/hr
Diluted polymer dose rateppm
PPM dose rate (undiluted)ppm
Total polymer required (batch)kg
Note: Polymer dose is highly tailings-specific and should be confirmed from bench / pilot flocculation trials, not a rule of thumb. Make-down dilution and pump duty are theoretical; verify against the dosing skid's operating envelope. Specific gravity assumes a single mineral phase.

Geobag Tailings Cost Model

Cost-per-dry-tonne (AUD/DMT) built from a solids mass balance, with every cost tied to a physical driver and split into tonnage-variable vs fixed/time-based.

Inputs

Blue = editable
1 · Project basis
dry t/yr
yr
d/yr
hr
2 · Tailings & dewatering
t/m³
3 · Geobag geometry & supply
m³/lm
m
$/lm
4 · Polymer
kg/t
$/kg
$/mo
5 · Labour
lm/shift
ppl
$/hr
ppl
$/hr
hr/d
$/hr
hr/d
$/hr
6 · Accommodation & mobilisation
ppl
$/n
frac
$
7 · Civil works
$/m²
$
$
8 · Equipment & pumping
$/mo
$
$/d
9 · Commercial
%

Results — base case

Live
Total installed cost$/DMT
Direct cost$/DMT
Total project cost$
Total dry tonnes storedDMT
Quantities
Geobag lineal metres requiredlm
Standard bag unitsno.
Deployment shiftsno.
Cost breakdown (direct)
$/DMT split
Tonnage-variable$/DMT
Fixed / time-based$/DMT
Sensitivity — $/DMT vs annual throughput
DMT/yr$/DMT total
Fixed costs are diluted as tonnage rises — which is why $/DMT falls across the scenario rows. The scenarios hold project life & all unit rates constant and vary only annual throughput.
Planning / comparison tool — figures are illustrative until project-specific inputs are populated. Replace geobag $/lm, polymer dose & $/kg, and all rental/labour rates with quoted / bench-tested values. Final dry density is the single biggest driver of stored volume — confirm it for your tailings. Excludes (unless added): return-water collection/treatment, double-handling, closure/capping, royalties, GST and finance costs. Commercial, contractual and regulatory matters should be verified with the relevant suppliers and advisors.

Geotextile Tube Fill-Height Calculator

Physics-first: maximum safe fill height is the lower of hoop tension, rolling stability and the geometric ceiling — no empirical fill-height table.

Inputs

Blue = editable
A · Slurry properties
B · Bag geometry
m
C · Fabric properties
kN/m
D · Engineering parameters

Results

Live
Derived slurry & geometry
Slurry density, ρ_mixkg/m³
Hydrostatic gradient, γkPa/m
Theoretical diameter, D = C/πm
Design tension, T_designkN/m
Calculated fill heights
Hoop-tension limitm
Stability limitm
Geometric ceilingm
Operating fill height, h_opm
Operating pressures
Base hydrostatic pressure at h_opkPa
Target pump pressure (90%)kPa
Hard pressure cap (105%)kPa
Capacity (volume per metre)
h/D at h_op
Volume / m at max pump heightm³/m
Volume / m at 75% settledm³/m
Capacity utilisation%
Method: h_max = MIN of three independent limits — (1) hoop tension h = √(T_design / (k·ρ·g)), independent of circumference; (2) stability h ≤ (h/D)_max·D; (3) geometry h ≤ D = C/π. Use pressure (kPa) for real-time operator control — it is more reliable than measuring height on imperfect foundations. After consolidation a second fill pass is usually possible; recalculate using the consolidated surface as the new datum. Always confirm with a bench / pillow test on the actual slurry where consequences of failure are material.

Geotextile Tube Volume Calculator

Volume from circumference & fill height using the empirical cross-section formula.

Inputs

Blue = editable
V = L · D² · [ (h/D)^0.815 − (h/D)^8.6 ]  where D = C / π
m
m
m
m

Results

Live
Theoretical diameter, Dm
Fill ratio, h/D (settled)
Cross-section area, A
Volume per metrem³/m
Total volume
Assumptions: D = C/π (theoretical diameter the section would have if filled to a full circle). Exponents 0.815 and 8.6 are an empirical fit — validate outputs against the manufacturer's published volume / fill tables before relying on them for design. Cross-section area peaks at h/D ≈ 0.74 then declines (a mathematical artefact of the form). Units are consistent-length agnostic (m → m³). General guidance only — confirm site-specific limits and good engineering practice.

Geotube Sizing & Dewatering Mass Balance

Tracks solids and water through three states — original slurry, pumped into the tube, and dewatered — then sizes the length and number of tubes required from the dewatered volume.

Inputs

Blue = editable
n = G(1−S) / [ G(1−S) + S ]  ·  V/m = D²·[(h/D)^0.815 − (h/D)^8.6]
Slurry & solids
%
%
%
Pumping
m³/hr
Tube selection
m
m
m
m

Results

Live
Mass balance
PropertyOriginalInto tubeDewatered
Tube sizing
Length of tube requiredm
Number of tubes (rounded up)units
Number of tubes (exact)units
Tube capacity
Theoretical diameter, D = C/πm
Volume / m at max fill heightm³/m
Volume / m at settled heightm³/m
Pumping
Volume pumped into tube
Time to pump at pump ratehr
Method: porosity n = G(1−S)/[G(1−S)+S] from solids SG (G) and solids mass fraction (S). Solids volume and bone-dry solids weight are conserved across all three states; water volume is recomputed at each state's porosity (water density = 1.0 t/m³). Tube volume per metre uses the empirical section formula (exponents 0.815 & 8.6, peak at h/D ≈ 0.74); validate against the manufacturer's published volume / fill tables before relying on it for design. Length required = dewatered volume ÷ settled volume per metre. Planning tool — confirm site-specific values and good engineering practice.